Ok so today I called the Buidling Dept for clarification on what is needed and their is some dispute over whether I've turned in the HVAC plans or not. David says I have, Jeff says I haven't. Will need to figure that one out?
But I got three manilla folders to catch all of the paperwork for each government office.
- I filled out the paperwork for the variance from County Sanitation
- Called ABC and clarified which documents I still need to fill out
- ABC (who are so nice and helpful, I KNOW it can be done) also told me to fill out the simple addendum to get a regular caterers beer/wine permit (so I don't have to go get one for every individual event)
- I gathered the documents I need to go copy tomorrow (facility lease)
- Have the address and procedure to go get a copy of my divorce paperwork
- Sent in the electronic copies of the blueprints to Fedex so I can pick up another copy tomorrow
- Talked at length to David today about the new floor plan to make the facility ADA accessible (front in particular)
- Did new visio diagrams with two different ramp options to make the facility ADA accessible and sent them to Stan and Dave
- Wrote my disclosure letter for the Building Dept
- Did a total BTU useage calculation for the Building Dept
- Emailed Stan and reminded him that he needs to write a letter saying I have permission to do the work I am doing
- Did a new Diagram of the restaurant for ABC
- Filled out the Gift/Loan form for ABC
I still have a full day tomorrow of running around, but I do feel like I got a little bit of the chaos under control today (WHEW!)
BTW here is the newest floor diagram (I know Stein will be interested!) of the possible ADA fix